- March 8, 2015:
- Brittany and I saw the aftermath winter had on our home and decided it was time to move to something more fitting of our current needs.
- Home search started.
- March 10, 2015:
- Contacted RH through the website and set appointment to meet with SR.
- March 11, 2015:
- Met sales rep and walked through our community's model (Palermo).
- Looked at numbers on a Palermo
- March 12, 2015:
- From our respective workplaces, we both found the Bateman plan on the RH website and started to become intrigued.
- March 14, 2015:
- Visited the Lysander Preserve development in Baldwinsville, NY and met with the rep there to tour the Venice model suggested by our SR.
- The rep at that model recommended checking out the Milan model because we could do it with a 3-bay garage (one of the things I really liked about the Bateman)
- Met with our SR again to run numbers on the Bateman and the Milan.
- March 15, 2015
- Met with SR to go over some requested discounts on the Bateman.
- Placed lot hold.
- March 18, 2015:
- Signed purchase agreement and made $5,000 deposit.
- March 23, 2015:
- Met with NVR Loan Officer
- March 28, 2015:
- Design Center / Selections Meeting (Added around $2500)
- April 2, 2015:
- Meeting with Electrician (Added aroud $4000)
- April 14, 2015:
- Received approval from NVR
- April 18, 2015:
- Made remaining Earnest Money Deposit
- April 27, 2015:
- Pre-Construction Meeting
- May 5, 2015:
- Site excavation started and completed.
- May 6, 2015:
- Footers formed and poured.
- May 7, 2015:
- Footer forms pulled.
- Stone laid in basement.
- Foundation walls formed and poured.
- May 8, 2015:
- Foundation forms removed.
- May 11, 2015:
- Site back filled around foundation
- Egress window shell installed
- May 21, 2015:
- Lumber delivered
- May 22, 2015:
- First floor beams placed
- Rim joist
- May 23, 2015:
- First floor framing began
- May 24, 2015:
- First floor framing continued
- May 25, 2015:
- Garage framing placed
- Second floor joists placed
- Staircases installed
- May 26, 2015:
- Second floor framing mostly completed
- Trussing installed on lower roof
- May 27, 2015:
- Almost all framing complete
- Roof sheathing complete
- Gables installed
- May 29, 2015:
- First site visit with PM
- Roofing materials delivered
- Electrical box placement started
--------
- June 1, 2015
- More electrical boxes placed
- June 2, 2015
- Recessed lights mounted
- June 5, 2015
- First layer of house wrap
- June 6, 2015
- Low voltage wiring box out
- Shingle Roof starter
- June 7, 2015
- Roof finished
- June 8, 2015
- Remaining house wrap applied
- Walk through with electrician
- June 9, 2015
- Mechanical work begins
- Electrical wiring begins
- Plumbing begins
- June 12, 2015
- Garage floor poured
- Basement floor poured
- June 13, 2015
- Relief cuts into basement and garage floors
- Low voltage wiring begins
- June 15, 2015
- Electrical rough finished
- Plumbing rough finished
- June 16, 2015
- Furnace installed
- Gas line installed
- Low voltage finished
- Insulation begins
- June 17, 2015
- Mechanicals finished
- Insulation finished
- Pre-Drywall Meeting
- June 18, 2015
- Inspections
- June 19, 2015
- ALL Drywall hung
- Siding started
- June 22, 2015
- Taping/Seaming started
- June 24, 2015
- Various deliveries
--------
- July 6, 2015
- Taping/Seaming Finished
- July 7, 2015
- Walls Primed
- Received Appraisal
- July 8, 2015
- Hard surface flooring started
- July 9, 2015
- Locked Interest Rate
- July 10, 2015
- Hard surface flooring completed
- July 13, 2015
- Trim carpentry begins (cabinets, molding, etc)
- July 15, 2015
- Cabinets mounted (the first time)
- Countertops set
- July 16, 2015
- Exterior trim and siding complete
- Gutters hung
- Interior painting
- July 17, 2015
- Interior painting
- July 18, 2015
- Low voltage trim plates installed
- July 19, 2015
- Carpet pad delivered
- July 20, 2015
- Carpet installation begins
- July 21, 2015
- Yard graded and seeded
- Driveway stone laid
- Carpet installation finished
- Shower tile work