  • March 8, 2015:
    • Brittany and I saw the aftermath winter had on our home and decided it was time to move to something more fitting of our current needs.
    • Home search started.
  • March 10, 2015:
    • Contacted RH through the website and set appointment to meet with SR.
  • March 11, 2015:
    • Met sales rep and walked through our community's model (Palermo).
    • Looked at numbers on a Palermo
  • March 12, 2015:
    • From our respective workplaces, we both found the Bateman plan on the RH website and started to become intrigued.
  • March 14, 2015:
    • Visited the Lysander Preserve development in Baldwinsville, NY and met with the rep there to tour the Venice model suggested by our SR.
    • The rep at that model recommended checking out the Milan model because we could do it with a 3-bay garage (one of the things I really liked about the Bateman)
    • Met with our SR again to run numbers on the Bateman and the Milan.
  • March 15, 2015
    • Met with SR to go over some requested discounts on the Bateman.
    • Placed lot hold.
  • March 18, 2015:
    • Signed purchase agreement and made $5,000 deposit.
  • March 23, 2015:
    • Met with NVR Loan Officer
  • March 28, 2015:
    • Design Center / Selections Meeting  (Added around $2500)
--------
  • April 2, 2015:
    • Meeting with Electrician (Added aroud $4000)
  • April 14, 2015:
    • Received approval from NVR
  • April 18, 2015:
    • Made remaining Earnest Money Deposit
  • April 27, 2015:
    • Pre-Construction Meeting
--------
  • May 5, 2015:
    • Site excavation started and completed.
  • May 6, 2015:
    • Footers formed and poured.
  • May 7, 2015:
    • Footer forms pulled.
    • Stone laid in basement.
    • Foundation walls formed and poured.
  • May 8, 2015:
    • Foundation forms removed.
  • May 11, 2015:
    • Site back filled around foundation
    • Egress window shell installed
  • May 21, 2015:
    • Lumber delivered
  • May 22, 2015:
    • First floor beams placed
    • Rim joist
  • May 23, 2015:
    • First floor framing began
  • May 24, 2015:
    • First floor framing continued
  • May 25, 2015:
    • Garage framing placed
    • Second floor joists placed
    • Staircases installed
  • May 26, 2015:
    • Second floor framing mostly completed
    • Trussing installed on lower roof
  • May 27, 2015:
    • Almost all framing complete
    • Roof sheathing complete
    • Gables installed
  • May 29, 2015:
    • First site visit with PM
    • Roofing materials delivered
    • Electrical box placement started
--------

  • June 1, 2015
    • More electrical boxes placed
  • June 2, 2015
    • Recessed lights mounted
  • June 5, 2015
    • First layer of house wrap
  • June 6, 2015
    • Low voltage wiring box out
    • Shingle Roof starter
  • June 7, 2015
    • Roof finished
  • June 8, 2015
    • Remaining house wrap applied
    • Walk through with electrician
  • June 9, 2015
    • Mechanical work begins
    • Electrical wiring begins
    • Plumbing begins
  • June 12, 2015
    • Garage floor poured
    • Basement floor poured
  • June 13, 2015
    • Relief cuts into basement and garage floors
    • Low voltage wiring begins
  • June 15, 2015
    • Electrical rough finished
    • Plumbing rough finished
  • June 16, 2015
    • Furnace installed
    • Gas line installed
    • Low voltage finished
    • Insulation begins
  • June 17, 2015
    • Mechanicals finished
    • Insulation finished
    • Pre-Drywall Meeting
  • June 18, 2015
    • Inspections
  • June 19, 2015
    • ALL Drywall hung
    • Siding started
  • June 22, 2015
    • Taping/Seaming started
  • June 24, 2015
    • Various deliveries
--------
  • July 6, 2015
    • Taping/Seaming Finished
  • July 7, 2015
    • Walls Primed
    • Received Appraisal
  • July 8, 2015
    • Hard surface flooring started
  • July 9, 2015
    • Locked Interest Rate
  • July 10, 2015
    • Hard surface flooring completed
  • July 13, 2015
    • Trim carpentry begins (cabinets, molding, etc)
  • July 15, 2015
    • Cabinets mounted (the first time)
    • Countertops set
  • July 16, 2015
    • Exterior trim and siding complete
    • Gutters hung
    • Interior painting
  • July 17, 2015
    • Interior painting
  • July 18, 2015
    • Low voltage trim plates installed
  • July 19, 2015
    • Carpet pad delivered
  • July 20, 2015
    • Carpet installation begins
  • July 21, 2015
    • Yard graded and seeded
    • Driveway stone laid
    • Carpet installation finished
    • Shower tile work